The original draft ruling was made on 18th of July 2019 as we noted here, with submissions to the draft determination closing on the 12th of September. A summary of stakeholder submissions to the proposed rule change can be found on the AEMC website.
It’s Sunday 24th October 2021 and the new Wholesale Demand Response Mechanism (WDRM) – perhaps better understood as a Centralised Negawatt Dispatch Mechanism – has commenced. On Friday 22nd October the AEMO noted: “This Sunday, 24 October, the National Electricity…
The AEMC has today announced that the proposed Wholesale Demand Response Mechanism (a.k.a ‘Negawatt Dispatch Mechanism’) is still on track to begin in October 2021. The AEMC’s press release stated that requests to delay the implementation timeline were considered due…
Submissions should be forwarded to AEMO by COB Friday 29 January 2021 on their Draft Report to consult on proposed amendments to Market and System Operation Procedures and Guidelines (Wholesale Demand Response).
On Thursday 25th March 2021 the AEMO published their Final Determination on the WDR Guidelines (which starts operating 24th October 2021). Here’s where you can find them.